Certificate of good performance
Municipality of Anton, Sofia Region
Reconstruction of 7 streets in Anton village – sidewalks 3,555 m², carriageway 7,956 m²
- Contract
- C28380
- Period
- 01/2022 – 03/2023
The reconstruction of 7 streets in Anton village was executed professionally and in full compliance with the design documentation and regulatory requirements. The crew worked in an organised manner and completed the project within the contracted 178-day period — delivering 3,555 m² of sidewalks and 7,956 m² of carriageway. We recommend ABM Consulting Ltd as a reliable partner for municipal infrastructure projects.
Signed by
Андрей Симов, Кмет на Община Антон